Please note that the provided timelines are estimates and subject to change due to the nature of construction work, which can be influenced by factors like weather conditions and unforeseen circumstances.
Last updated: Novembre 11, 2025
Overhead Electrical Work – Rue Heath
Hydro-Québec will be conducting overhead electrical work on Rue Heath.
📅 Date: November 22, 2025
🕗 Time: 7:00 a.m. – 5:00 p.m.
👷♂️ Teams on site: 10 Hydro-Québec jointer crews
🚫 Parking restrictions apply during the operation.
Closures include:
Excavation work on Croissant Merton will result in alternating temporary road closures and parking restrictions within the work zone from November 11 to 14. Certified traffic flaggers will be on site to assist with circulation and ensure safety throughout the operation.
Due to recent heavy rainfall, the temporary closure of Rue Stratford near Chemin Adelaide will continue on Thursday, November 6, and Friday, November 7, from 8:00 a.m. to 2:00 p.m.
A certified traffic flagger will be on site to ensure safe circulation. Signage and equipment will be removed outside working hours to minimize impact on local access.
The Town of Hampstead thanks residents for their patience and understanding.
Hydro-Québec Work – Rue Fallbrook & Croissant Netherwood
Hydro-Québec will be conducting electrical work to replace equipment in the area of Rue Fallbrook (near the centre of the street) and Croissant Netherwood (near the curve).
📅 Date: November 10, 2025
🕗 Time: 8:00 a.m. – 4:00 p.m.
⚡ Work Type: Transformer replacement
👷♂️ Teams on site: 3 Hydro-Québec jointer crews
Traffic may be slowed in the immediate work zone and no parking permitted on both sides of the street within the work area will be in effect. Please use caution near workers and equipment.
Hydro-Québec will carry out overhead electrical work on its network. These operations are necessary to maintain the reliability of the electrical infrastructure.
📅 Date: November 4, 2025
🕗 Time: 12 p.m. to 4 p.m.
📍 Location: Croissant Netherwood
🚧 Traffic and Parking Restrictions:
• Partial closure eastbound on Croissant Netherwood between the Croissant Aldred intersections
• Full closure of the sidewalk adjacent to the work zone
• No parking permitted on both sides of the street within the work area
As part of its major yearly initiative, the Town of Hampstead will undertake the rehabilitation of its roads and sidewalks. This substantial investment is intended to preserve the durability, safety, and overall quality of municipal infrastructure.
Sectors concerned
(Work will be carried out simultaneously across the four sectors of the Town.)
Work period
From September 2 until early November 2025, weather permitting and subject to project progress.
📅 Schedule: weekdays, daytime hours.
Please note that dates are subject to change.
Key information
📞 For any questions, please contact Town Hall at 514-369-8200.
🚨 To report any issues, please reach out to Public Security at 514-369-8250.